Rolling Production Planning in Jordan | Masna3y Pro
Six steps to build a rolling production plan, freeze near-term orders, and reconcile materials and capacity. Includes a worked example and Jordanian context.
Rolling Production Planning for Factories in Jordan
Build a rolling production plan and review it every week. Freeze near-term orders once materials and setups are committed, and keep later weeks flexible. A rush order should only enter the frozen window if materials and capacity are available and the impact on existing delivery commitments is understood.
How to use Jordan’s Industrial Production Index
Jordan’s Department of Statistics release of 11 November 2026 reported that the general Industrial Production Index rose 4.45% in September 2026 from September 2025, but fell 2.54% from August 2026. It was 1.05% higher in the first nine months than in the same period of 2025. These figures describe changes in a national index, not a factory’s order volumes or sales forecast. Use them as sector context; use confirmed orders and available capacity to decide what to run next week.
Six steps to implement a rolling plan
- Split the horizon. Start with one or two frozen weeks, four flexible weeks, and an indicative horizon for long-lead materials, up to 13 weeks in total if useful. Adjust the windows to actual lead and setup times.
- Calculate usable capacity. Deduct maintenance and setup hours from machine time. Pick a consistent unit, such as pallets or machine hours, and exclude reserved or quality-held quantities from available stock.
- Hold a short weekly review. Bring confirmed new orders, free materials, usable hours, and the list of orders that would move if a rush job were accepted. Record a responsible person and date for each change, and retain the original weekly plan.
- Require a decision for exceptions. Check materials, capacity and downstream delivery impact. Price overtime or rescheduling before making the commitment, or offer a feasible later slot.
- Separate variability from safety stock. Measure demand variability over comparable weeks. A stocking decision also needs supplier lead time, lead-time variability, target service level, and stockout costs. Do not convert a weekly demand variance directly into safety-stock units.
- Connect materials to production. Reserve inventory for near-term orders and check expected receipts for later orders. Log the reason for any deviation, such as a rush request, shortage, breakdown, quality hold or inaccurate run time.
Illustrative example: a detergent factory
Hypothetical weekly demand in pallets over eight weeks was 120, 95, 140, 110, 160, 100, 130 and 125. The total is 980, the mean is 122.5, and the mean absolute deviation is 16.25 pallets. The last number describes variability in this sample; it does not establish a 16-pallet safety stock.
If eight of ten frozen orders were finished in the week originally planned, schedule adherence was 80%. Track it alongside changes within the freeze and machine hours lost to material shortages. Review root causes with production, procurement and sales before assigning blame.
What if you manufacture to order?
Freeze committed machine operations or milestones rather than assumed repeat quantities. Plan uncommitted capacity and common inputs on a flexible horizon.
Read the Arabic guides to production orders and purchasing from the production plan. To discuss a test scenario for your factory, request a Masna3y Pro trial.